Lisha Kill

Lisha Kill

Client: Town of Colonie
Location: Colonie, NY
Design: Delaware Engineering
Market: Waste Water

Project Profile

Approximately $2.3M of sewage pump station renovation consisted of the demolition of (3) 40-year old pumps and associated systems and their replacement with (4) new 200HP 3,400GPM pumps. Additionally, a mechanical bar screen with a washer/compactor, built to handle 1.8MGD of average daily flow, was installed for which the construction of a new mezzanine level was required. An odor control system handling 5,000 SCFM of total air flow and providing 99.9% removal of hydrogen sulfide was also installed along with new controls and security systems.  Complete pump station flow by-pass operations were required in order to perform much of the pump replacement work. BCI self-performed all equipment installation as well as the concrete, by-pass, and site work.